Steel Partition Office and mezzanine FLoor

Location: City of London, EC

Client Background: BSE UK, a leading provider of bespoke workplace solutions, was approached by a prestigious global financial institution to address their need for a print room installation within the basement of their central London offices.

Challenges: The client required a comprehensive solution involving the design and installation of a new mezzanine floor along with associated fit-out works. The project was time-sensitive, demanding a swift and efficient one-stop-shop fit-out solution.

Scope of Works:

Mezzanine Floor Installation:

  • Delivered and installed a 100m2 storage mezzanine floor in the basement of the central London offices.
  • Implemented 1-hour fire protection measures for the mezzanine floor.

Office Fit Out:

  • Installed floor coverings in the newly designated office area.
  • Provided a full design and installation of Mechanical & Electrical (M&E) package, including MVHR system, AC equipment, ductwork, and extraction.
  • Implemented a new Distribution Board, LED Lighting, and Lighting Control systems.
  • Installed Small Power, Fire alarm, and data infrastructure with primary containment.
  • Utilized Double Skin Steel Partitioning to create a print room below the mezzanine floor.

Building Regulations Compliance:

  • Submitted Building Regulation Application and obtained necessary approvals.
  • Ensured compliance with all regulatory standards and obtained official sign-off.

Floor Painting and Defined Zones:

  • Applied 100m2 of floor painting to create well-defined maintenance zones and pedestrian walkways.

Project Management:

  • Provided full project management services to ensure a seamless and timely execution of the entire project.

Results:

Through collaborative efforts with the client, BSE UK successfully delivered a high-quality mezzanine floor and fit-out solution within the stringent timelines. The project not only met the client's specific requirements but also adhered to all relevant regulations, ensuring a safe and compliant workspace.

Check out our gallery below featuring a few photos during the works.

Contact us

Bristol Storage Equipment Limited
Unit 2, Severnlink Distribution Centre,
Chepstow, NP16 6UN

Sign up to receive our newsletter

By submitting this form you agree to our privacy and data protection policy which governs how we deal with personal data.

Get in touch

    Scroll To Top